Timeline

Preliminary "stuff"

09/13 - Signed contract
09/17 - Met with NVR
09/22 - Flooring selections
09/25 - Guardian meeting
10/17 - Loan approval
10/22 - Preconstruction meeting
11/2 -   Silt fence installed

Construction

Week 1:
Day 1 (11/6):      Groundbreaking
Day 3 (11/8):      Footers
Day 4 (11/9):      Basement walls poured
Day 5 (11/10):    Forms removed

Week 2:
Day 9 (11/14):    Waterproofing
Day 10 (11/15):  Drain Tile
Day 11 (11/16):  Plumbing
Day 14 (11/19):  Backfilled
Day 15 (11/20):  Slabs prepped
Day 16 (11/21):  Slabs poured

Week 3:
Day 21 (11/26):  Framing started (delayed from 11/23 due to Thanksgiving holiday)
Day 22 (11/27):  No framing - rainy weather
Day 23 (11/28):  2nd floor framed, most windows installed
Day 24 (11/29):  Roof and porch roof (no shingles); house wrapped
Day 26 (12/1):    HVAC

Week 4:
Day 29 (12/4):    Plumbing, Guardian appt
Day 30 or 31:     Shingles
Day 31 (12/6):    Gas & electric
Day 33 (12/8):    Wiring by Guardian
Day 35 (12/10):  Pre-drywall meeting
Day 36 (12/11):  Insulation installed

Week 5:
Day 37 (12/12):  Drywall delivered
Day 40 (12/15):  Drywall hung
Day 43 (12/18):  Siding started

Week 6:
Day 45 (12/20):  Siding and shutters complete, sidewalk and porch steps, stone fireplace
Day 49 (12/24):  Heat on & walls painted primed
Day 51 (12/26):  Trim, railings, cabinets, vanities, and mirrors installed
Day 52 (12/27):   Porch columns installed; trim work continues

Week 7:
Day 54 (12/29):  Paint (1st coat)
Day 56 (12/31):  Tile

Week 8:
Day 59 (01/03):  Granite counters, vinyl flooring, subfloors sanded
Day 60 (01/04):  Interior door knobs; metal porch roof
Day 63 (01/07):  Electricians install lighting & outlets, driveway laid, gutters
Day 64 (01/08):  Stove & microwave installed; Guardian finishes
Day 65 (01/09):  Hardwood floors, touch up paint & drywall
Day 66 (01/10):  Carpet, toilets, faucets, basement insulation, exterior lighting & paint

Week 9:
Day 67 (01/11):  Hardwood finished, water lines connected, yard graded


Planned:
Day 86 (01/30):  Final walkthrough
Day 108 (02/22):  Closing



Click here for Ryan Homes' timeline




No comments:

Post a Comment