09/13 - Signed contract
09/17 - Met with NVR
09/22 - Flooring selections
09/25 - Guardian meeting
10/17 - Loan approval
10/22 - Preconstruction meeting
11/2 - Silt fence installed
Construction
Week 1:
Day 1 (11/6): Groundbreaking
Day 3 (11/8): Footers
Day 4 (11/9): Basement walls poured
Day 5 (11/10): Forms removed
Week 2:
Day 9 (11/14): Waterproofing
Day 10 (11/15): Drain Tile
Day 11 (11/16): Plumbing
Day 14 (11/19): Backfilled
Day 15 (11/20): Slabs prepped
Day 16 (11/21): Slabs poured
Week 3:
Day 21 (11/26): Framing started (delayed from 11/23 due to Thanksgiving holiday)
Day 22 (11/27): No framing - rainy weather
Day 23 (11/28): 2nd floor framed, most windows installed
Day 24 (11/29): Roof and porch roof (no shingles); house wrapped
Day 26 (12/1): HVAC
Week 4:
Day 29 (12/4): Plumbing, Guardian appt
Day 30 or 31: Shingles
Day 31 (12/6): Gas & electric
Day 33 (12/8): Wiring by Guardian
Day 35 (12/10): Pre-drywall meeting
Day 36 (12/11): Insulation installed
Week 5:
Day 37 (12/12): Drywall delivered
Day 40 (12/15): Drywall hung
Day 43 (12/18): Siding started
Week 6:
Day 45 (12/20): Siding and shutters complete, sidewalk and porch steps, stone fireplace
Day 49 (12/24): Heat on & walls
Day 51 (12/26): Trim, railings, cabinets, vanities, and mirrors installed
Day 52 (12/27): Porch columns installed; trim work continues
Week 7:
Day 54 (12/29): Paint (1st coat)
Day 56 (12/31): Tile
Week 8:
Day 59 (01/03): Granite counters, vinyl flooring, subfloors sanded
Day 60 (01/04): Interior door knobs; metal porch roof
Day 63 (01/07): Electricians install lighting & outlets, driveway laid, gutters
Day 64 (01/08): Stove & microwave installed; Guardian finishes
Day 65 (01/09): Hardwood floors, touch up paint & drywall
Day 66 (01/10): Carpet, toilets, faucets, basement insulation, exterior lighting & paint
Week 9:
Day 67 (01/11): Hardwood finished, water lines connected, yard graded
Planned:
Day 86 (01/30): Final walkthrough
Day 108 (02/22): Closing